Score: 0 Reference
1)For some of the tasks, I would like to "complete" them in a .failed. state to better track some of the goals I have.

Is that possible?

For example I would like to add the option to "fail" a task in addition to the change, remind later and complete options.

2)Also I am wondering what a good method might be to export my data and look at my todo history in a vizualized way.

Any tips?
Jake

Toodledo Founder
Posted: Dec 02, 2012
Score: 0 Reference
1) You could use tags for this, or just mark it in the note. You could also move it to a "failed" folder. There are a variety of ways, maybe one of these will work for you.

2) In our Tools section, there are a variety of export options, including CSV which can be opened in Excel and then graphed.
daniel_h

Posted: Dec 04, 2012
Score: 0 Reference
I use the status "Canceled" for this. I mark it complete but change the status to canceled, and add annotate the note field.