When I view my todo list in the Context view (viewing one specific context) with subtasks flattened it shows 31 tasks and 109 hours (which is correct).
When I show subtasks indented the context view says there are 17 tasks (not counting the sub tasks) and claims there are only 63 hours (not counting any of the sub tasks length). This is a bit frustrating cause I have to change back to flattened view to get the hours remaining.
I hope you can fix it so that the context total length counts subtasks even when indented, or by changing parent tasks to automatically have the accumulated length of all it's subtasks.
|
Jake
Toodledo Founder
|
This is a bug that we are planning to fix. It is actually a bit complicated, but we are working on it.
|