Is there any way to include tasks with No Due Date in hotlist (along with other criteria such as Today's tasks)?

The reason for this is that there are tasks that need to be done on a specific day--those get a due date and show up on the Hotlist as needed. There are other tasks that need to be done but the timing is flexible. I'd still like to see that they're there, and showing these on the Hotlist view keeps them in sight since I spend 99% of the time on the Hotlist view.
JPR

Posted: Mar 09, 2013
Score: 0 Reference
The only options to control your Hotlist are:

• priority of at least X
• due date within the next X days
• star = yes
• status = "Next Action"

A task only needs to match one of the above to show on the Hotlist. So for No Due Dates, you'll need to use either Priority, Star or Next Action.

You can override all of these using a Start Date.