ForumsQuestionsDue Date & Repeeting Tasks


Due Date & Repeeting Tasks
Author Message
frankie.toodle

Posted: Jan 12, 2017
Score: 0 Reference
Hi Folks,

I am pretty sure, this question has been asked before, but I was unable to find it using search.

If I have a repeating task including a start and due date. How will those be set, when the task is repeated?

Example:

Start Jan 1, due Feb 1, repeating Yearly from Due Date.
If this Task is completed, what will the repeating tasks dates be?
a) just like above
b) Start Feb 1, due Mar 1

Many thanks in advance.
Jake

Toodledo Founder
Posted: Jan 12, 2017
Score: 0 Reference
The task moves forward based on the due-date and then the start-date is moved forwards the same amount so that the difference between start-date and due-date remains the same.
frankie.toodle

Posted: Jan 13, 2017
Score: 0 Reference
So a yearly recurring task will be due always on the same date, correct?
Adrien Beau

Posted: Jan 13, 2017
Score: 1 Reference
This is correct if you use the default recurring settings (repeat based on the due date). In that case it will add one year to the due date, so it will be on the same day.

You can also set it to recur based on the completion date, in that case it will add one year on the day you mark the task complete (maybe several days after the completion date).
You cannot reply yet

U Back to topic home

R Post a reply

To participate in these forums, you must be signed in.